After 1 failed inspection, and 1 cancelled inspection, the plumbing rough was approved today, so the foundation can be started. This'll prolly be early/mid next week, then time to dry, and inspection; they could start the frame the last week of the month.
Posted by haglund at August 22, 2002 3:02 PM